Decision Step |
Entry Point |
|
|
Decision Step |
|
Optional |
Decision Step |
|
|
|
Phase II - VRP (2) |
Appears Clean - Complete Report (Solicit NFA letter
and certificate of completion from State) |
|
|
|
State Declines Application - Revise application or
withdraw |
|
|
State Declines - Revise plan or withdraw |
|
|
| Appears Dirty - Prepare written Remedial
Action Plan with Remedial Application. |
Environmental Remediation Contractor Selected |
Develop cost estimate for remedial action plan |
Develop Remedial Action Plan (RAP) and Apply for
Voluntary Remediation Program. |
LDEQ Accepts Application |
Public Review, Distribution, Notice, and Comment
along with Specific Landowner Notice on VRP for Pilot Site |
Public Comment may Indicate need for Hearing or Plan
Revision |
State Approves with acknowledgement that upon
certificate of completion applicant may receive release of liability from
State. |
Total Time (Days) & Cost ($1000) |
Continue to Cleanup |
|
What |
Participant selects from qualified contractors |
|
Submit VRP Application with required fees and a
Voluntary RAP to include: (1) remedial investigation report, (2) remedial
design, and (3) remedial project plan. Remedial design should implement the
proposed remedy that will attain the Remedial Action goa |
|
Applicant provides copies to State and local public
facilities. Legal notice of proposed RAP published. Notice sent to
contiguous property owners. Comments accepted for 30 days and considered by
State. |
Based on public comments, State will determine if a
public hearing or plan revision is needed. |
State considers/responds to public comments. If
plan revisions are necessary, participant, Pilot City notified and make
appropriate modifications. Modified plan approved by State. |
|
|
|
Who |
Participant, Pilot |
Contractor |
Contractor, Pilot City |
|
Community, Applicant, Pilot City, State |
State& Community |
State |
|
|
|
Time |
1 |
7 |
45 |
|
30 |
30 |
45 |
320 |
|
|
Initiating Action |
Verbal or written participant commitment to VRP |
Pilot City issues written request for work plan cost
estimate |
Piloit City authorizes cost estimate |
|
State acceptance of RAP. |
State determines if necessary based on public
comment and other information. |
Where approved remedial action incorporates
restrictions or controls, certificate is subject to compliance with
restrictions or controls. Certificates issued to responsible party for site
remediated for industrial use are valid only for industrial use. |
|
|
|
Cost |
$0 |
$0 |
20,500 |
|
Minimal |
minimal |
$0 - $5,000 |
71 - 79 |
|
|
Available Assistance |
Pilot screens contractor credentials for quality
assurance |
May be prepared by Pilot City |
RAP cost may be covered by Pilot grant. Participant
responsible for State application fee. |
|
Cost may be covered by Brownfields Pilot grant |
|
n/a |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|