Phase II ESA Using ASTM
        Decision Step Decision Step  
        Appears Clean - (NFA letter from LDEQ may be requested) Appears Dirty - indicating need for Clean up Plan  
Activity ASTM Work Plan with cost estimate & scope of services. Prepare written QAPP for US EPA Conduct Phase II Written Report on Pilot Site Establish remedial action plan using State Voluntary (VRP) process Total Time (Days) & Cost ($1,000)
What ESA following standardized ASTM E-1903-97 guidelines with the inclusion of a cost estimate and general description of proposed assessment procedures for Pilot site. Quality Assurance Project Plan (QAPP) required by EPA to establish data collection objectives and assure usefulness of data. Study of recognized environmental conditions at pilot site including environmental sampling Evaluation of recognized environmental conditions with professional opinion regarding hazardous substance release or disposal at Pilot site for decision making Will likely require additional sampling to establish site-specific Risk-based cleanup levels.  
Who Contractor Contractor or Pilot City & EPA. Contractor Contractor Pilot City, Contractor, and LDEQ.  
Time (Days) 14 35 60 14 320 443
Initiating Action Pilot City submits written request for Work Plan. Scope of services approved. QAPP approved by EPA Finalization of research Data deficiencies in ASTM Phase II.  
Cost Estimate $8,000 Included in Work Plan $20,000 Included w/ Phase II. $40,000 to 50,000 68 - 78
Available Assistance Pilot City outlines needed scope of services. Cost may be covered by Grant.   Pilot over-sees field work. Cost may be covered by Grant Pilot City reviews and confers with participant. Cost possibly covered. Pilot reviews and confers with participant and agencies. Cost possibly covered.