Phase I Environmental Site Assessment (ESA)
      Decision Step Decision Step  
"Defined" Exit Points in Process     No Recognized Environmental Conditions for Pilot Site (solicit NFA letter from LDEQ) Withdraw from Program.
ACTIVITY OR EVENT Environmental Assessment Contactor Selected Conduct Phase I ESA Phase I Report on Recognized Environmental Conditions Phase II (ASTM or VRP) ESA Indicated Total Time (Days) & Cost ($1,000)
What Participant selects from qualified contractors. Standardized ASTM E-1527-00 assessment. standardized ASTM E-1527-00 report. Continue to Phase II.  
Who Participant, Brownfields Coordinator Participant, Brownfields Coordinator & Contractor Contractor    
Time (Days) 1 7 7   15
Initiating Action Pilot application form complete. Pilot City authorizes work. finalization of research    
Cost Estimate n/a $1,500 - 1,800 Included w/ Phase I   $1,500 - 1,800
Available Assistance Pilot/provider screens contractor credentials for quality assurance Pilot inventory may provide additional information Pilot Cityr reviews and confers with participant.